Thompson, MB

Completion Date

2012

Tonnage

2500

GC

O.N.E. Partnership

Owner

Manitoba Hydro

Wuskwatim, Manitoba Hydro

Wuskwatim is a 200-megawatt, run-of-river hydroelectric generating station on the Burntwood River at Taskinigup Falls.  800km north of Winnipeg.

Construction of the generating station was completed in late 2012 at a cost of $1.3 billion.
 

  • 2500 tonnes of structural steel.

  • Installed steel structure, cladding and overhead cranes.

  • 0 LTI’s

  • project completed on schedule​

  • GC consisted of H.J. O’Connell Limited , Neilson Inc. and EBC Inc.