707 Fifth, Manulife Place
Location
Calgary, Alberta
Completion Date
2017
General Contractor
EllisDon
Architect
SOM
Tonnage
4500
The new home to Brion Energy will be a 27-storey, 564,000 square foot, "AAA", LEED Gold Certified office tower. 707 Fifth Street's distinct elliptical form, with floor-to-ceiling glass, is designed to maximize panoramic views of the city and the Rockies.
The concrete-core, steel framed office tower was completed in 2017.
​
Design Assist Elements
-
Developed an adjustable curved bent plate system at the slab edge.
-
Performed embed surveys and fabricated on site shim plates to capture the precise geometrical angle needed.
-
Recommended 70 ksi steel for the lower columns.
-
Redesigned (4) 46-tonne, below-grade transfer girders to accommodate the tower crane capacity and working radius.
-
Provided input and sourced oval HSS mullions from Europe for the sawtooth entryway.
-
Proposed a modular built-up box lift for the AESS steel in the Winter garden
​
Finalist for the 2017 CISC Award in Architecture